Capstone Summary May 28, 2010
My project was completed on time. Problems which arose were due to the voice over which My client wished to have in the animation, not its presence but when it was given to me; while im sure it was brief as possible the times spent on each scenes explanation often did not mirror the animations length making the animation need editing for them to sync up.
Do to the animations simple nature I was able to complete the animation relatively fast however the time spent was often situated around making the animations accurate as it was meant to be more a diagram then a story.
I kept everything simple using what I knew worked so my only technical difficulty was the addition of sound that I did research on during the last weekend within the term.
In Conclusion an Uneventful yet complete term that should leave everyone happy.
Friday, May 28, 2010
Friday, May 7, 2010
blog log week 2
Week 2
Day 6
-Created Volcano BG
-answered 2 emails
Day 7
-Learned animation through the shape tween
-Animated scene one, to have it not work properly
Day 8
-Animated Scene 1
-Answered 3 Emailes
Day 9
-Revised scene one
-Answered 2 emails
Day 10
-revised scene one
-scene 2 bg
-began scene 2 animation
-Answered 1 Email
Day 6
-Created Volcano BG
-answered 2 emails
Day 7
-Learned animation through the shape tween
-Animated scene one, to have it not work properly
Day 8
-Animated Scene 1
-Answered 3 Emailes
Day 9
-Revised scene one
-Answered 2 emails
Day 10
-revised scene one
-scene 2 bg
-began scene 2 animation
-Answered 1 Email
Monday, May 3, 2010